Week 5 - Introductory HVAC
- Santos
- Jun 8, 2020
- 1 min read
Finding CFM-
V(room)= L*W*H = ____ cuft
V(air)= 3.5ACH* V(room) = ____ cuft per hour
V(air) / 60min/hr = _____ CFM cuft per min
Example-
30L*15W*9H = 4050 cuft V(room)
3.5*4050 = 14,175 cuft per hour V(air)
14,175 / 60 = 236.25 CFM cuft per min
Finding Profit-
Add up Parts total =____ (all parts)
Add up Labor= ____ (hours*wage)
Add up Overhead= ____ (overhead*hours)
Add up Parts, Labor, and Overhead = _____
Subtract total Sell Price of job by above equals Profit = _____
Profit divided by Sell Price =____
Covert to percentage=____
Example-
Parts Total= $2730.28
Labor= $852.50
Overhead= $2250.00
$2730.28+$852.50+$2250.00= $5832.78
Sell Price= $6357.73
$6357.73 - $5832.78 = $524.95
524.95 / 6357.73 = 0.08 = 8% profit
Measuring-
K kg kl km
H hg hl hm
D dag dal dam
B g l m
D dg dl dm
C cg cl cm
M mg ml mm
King Henry Died By Drinking Chocolate Milk
Fahrenheit to Celsius-
· Subtract 32 from F temp
· Take answer multiply by 5
· Take answer divide by 9
· Answer in C
Celsius to Fahrenheit-
· Multiply C by 9
· Take answer divide by 5
· Take answer add 32
· Answer in F